ENGINEERING BUILDING

PROJECT OWNER: Grand Canyon University


LOCATION: Grand Canyon University Campus


CONSTRUCTION DATES: August 2015 - October 2016


DESIGN FIRM: SuoLL Architects


FIVE MAJOR SUBS:

i. Suntec Concrete
ii. Marlin Plumbing
iii. Hilty’s Electric
iv. Bell Steel
v. Stone Cold Masonry


PROCUREMENT METHOD: Design-Assist Negotiated Contract Price

BIGGEST CHALLENGE OF THE PROJECT: The project schedule on this building was expedited further than usual which necessitated the building be completed in phases so as to occupy a portion of the building earlier than originally planned. The second phase was then completed while the first phase was fully occupied. This first phase which consisted of approximately 80KSF was completed in six months. The second phase was then completed in 14 months. Final complete project schedule for the fully occupied building was 16 months start to finish.